Corsham Technology Park Phase 2

 

Summary:

High security data storage facility

 

Sector:

Commercial

 

Services:

Substructures, drainage, services and external works

 

Client:

Ark Data Centres

 

Main Contractor:

H Sweet and Sons

 

Start Date:

October 2013

 

Location:

Corsham, Wiltshire

 

Value:

£2,000,000

Scope of our works: Mass fill concrete (3500m3) to underside foundations down to bedrock, reinforced foundations. External works including tarmac roads, permeable paving, truckpave, kerbs and edgings, topsoiling. Drainage incorporating 1000m of drainage runs, drainage channels, petrol interceptors and attenuation tank. Services comprising 1500m trenching, equipment bases and service pits.